Name of BRTS Project - Kalewadi to Dehu Alandi |
|
|
|
|
Packages in the Project |
Length in Km |
Source of funding |
Right of Way (RoW) |
Current Status |
Package I - Construction of BRTS corridior From Kalewadi Phata on Aundh Ravet Road to Chinchwadgaon Bridge Phata. Chainage 0/000 to 1/600 |
1.6 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (35% complete) |
Package II - Construction of BRTS corridior From Chinchwadgaon Bridge Phata to Pawana River Bridge Approach. Chainage 1/600 to 2/800 |
1.2 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (Just started) |
Package III - Construction of River Bridge, Flyover, ROB upto Auto cluster gate. Chainage 2/800 to 4/800 |
2 km |
World Bank-SUTP |
45 meter |
In progress (Just started) |
Package IV - Construction of BRTS corridior From Auto Cluster Gate to KSB Chowk on Telco Road. Chainage 4/800 to 6/480. |
1.68 km |
Jnnurm (Central, State and Corporation) |
45 meter |
Not Started |
Package V - Construction of BRTS corridior From KSB Chowk on Telco Road to Dehu Alandi Road Via Kudalwadi. Chainage 6/480 to 10/275. |
3.79 km |
Jnnurm (Central, State and Corporation) |
45/25 meter |
In progress (30% complete) |
|
|
|
|
|
Name of BRTS Project: Nashik Phata to Wakad |
|
|
|
|
Packages in the Project |
Length in Km |
Source of funding |
Dispute in Awarding of Bid |
Current Status |
Construction of flyover at Nashik phata |
2.12 km |
World Bank-SUTP |
45 meter |
In progress (12% Completed) |
Construction of Road BRTS from nashik phata flyover approach to Kaspate vasti. |
4.85 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (50% completed) |
Construction of Road BRTS from Kaspate vasti to wakad(westerly bypass) . |
2.12 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (40% completed) |
|
|
|
|
|
Name of the BRTS Project - Mumbai Pune |
|
|
|
|
Packages in the Project |
Length in Km |
Source of funding |
Dispute in Awarding of Bid |
Current Status |
Construction of Mumbai Pune Road from Harris bridge Dapodi to Nashik Phata junction in PCMC limit |
12 km |
Jnnurm (Central, State and Corporation) |
61 meter |
Completed |
Construction of Mumbai Pune Road from Ahilyabai Holkar Chowk to Chinchwad |
Jnnurm (Central, State and Corporation) |
61 meter |
Completed |
Construction of concrete pavement & related works for Mumbai end of Chinchwad grade separators to Nigdi octroi post excluding the grade separator |
Jnnurm (Central, State and Corporation) |
61 meter |
Completed |
|
|
|
|
|
Name of the BRTS Project - Aundh Ravet |
|
|
|
|
Packages in the Project |
Length in Km |
Source of funding |
Dispute in Awarding of Bid |
Current Status |
Improvement of Aundh Ravet road. Section - I road 0/000 to 2/000 |
2 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (32% completed) |
Improvement of Aundh Ravet road. Section - II road 2/000 to 3/900 |
1.9 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (29% completed) |
Improvement of Aundh Ravet road. Section - III road 3/900 to 5/900 |
2 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (74% completed) |
Improvement of Aundh Ravet road. Section - IV road 5/900 to 7/700 |
1.8 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (69% completed) |
Improvement of Aundh Ravet road. Section - V road 7/700 to 9/500 |
1.8 km |
Jnnurm (Central, State and Corporation) |
45 meter |
In progress (80% completed) |
Improvement of Aundh Ravet road. Section - VI road 9500 to 12/000 |
2.5 km |
Jnnurm (Central, State and Corporation) |
30 meter |
In progress (79% completed) |
Improvement of Aundh Ravet road. Section - VII road 12/000 to 14/500 |
2.5 km |
Jnnurm (Central, State and Corporation) |
30 meter |
In progress (80% completed) |